This Essbase discussion board is provided as a free service and dedicated to all the Essbase professionals out there!
 Return to Index  

Re: Calculate week & working days in month

August 7 2012 at 8:26 AM
No score for this post
Sean V 
from IP address 166.248.8.188


Response to Calculate week & working days in month

I maintain a static file which I load into cubes requiring this. Elegant solution? no. But it works...

 
Scoring disabled. You must be logged in to score posts.Respond to this message   
Responses

  1. I agree with Sean - Cameron Lackpour on Aug 7, 8:36 AM
    1. Also Agree - Stuart Game on Aug 8, 6:24 AM
     
  2. Calculate week & working days in month - hyppool on Aug 7, 9:18 AM
    1. Another reason to preload it - whose holidays - DanP on Aug 7, 3:13 PM
    2. Re: Calculate week & working days in month - Jeff McAhren on Aug 8, 9:17 AM
     

RSS feed for this forum - http://www.network54.com/Forum/58296?xml=rss. Please email hypess (at) gmail.com, if you have any questions/feedback/issues.